Project Results by SEI Level
|
|
Calendar
|
Effort
|
Total cost (US$ 000)
|
|
SEI level
|
time
(months)
|
(Person months)
|
(median)
|
(lowest)
|
(highest)
|
|
I
|
29.8
|
593.5
|
5,440
|
1,786
|
101,721
|
|
II
|
18.5
|
143.0
|
1,311
|
962
|
1,732
|
|
III
|
15.2
|
79.5
|
728
|
518
|
933
|
|
IV
|
12.5
|
42.8
|
392
|
279
|
502
|
For the code and test phases only
of a typical 200,000-line business application.
Project Results by SEI Level
(cont.)
|
|
Calendar
|
Effort
|
Defects
|
Total cost
|
|
SEI level
|
time (months)
|
(Person months)
|
Discovered
|
Shipped
|
US$ 000
(median)
|
|
I
|
29.8
|
593.5
|
1,348
|
61
|
5,440
|
|
II
|
18.5
|
143.0
|
328
|
12
|
1,311
|
|
III
|
15.2
|
79.5
|
182
|
7
|
728
|
|
IV
|
12.5
|
42.8
|
97
|
5
|
392
|
Defect counts
include all phases up to final customer shipment.
All contents © copyright Master Systems Inc. Please respect the copyright.
If you reprint or republish the table please be sure to include the copyright notice.
To download more information about this table and its derivation, please
click here.